Nevada Project State — 3 public-record projects
As of 5 November 2026, this project docket had been quiet for 106 days.
Vantage NV11’s own utility docket had no filing since 22 July 2026. During those 106 days, the separate proceeding its filings say it is waiting on issued four orders.
Dated steps: supplemental testimony 2 October 2026 (passed); Phase II hearing 26 October 2026.
This establishes where the dependency is recorded and what changed afterward. It does not establish delay, outcome, or what any company knows.
Ask us to do this for a project of yours · see the live view
Verify the Vantage records
3 Nevada projects shown from published public records: what each one is waiting on, what the records establish, and what they do not. Every state carries its own observation date; the oldest is 15 September 2026.
A dependency stated in one docket and advanced in another
9 records from the Public Utilities Commission of Nevada, each carrying its own extent and observation date. Figures below are as of 5 November 2026.
The project's own proceeding, Docket 26-05028, has had no filing since 22 July 2026 — while the separate case it is waiting on has moved four times.
The Commission's 24 September 2026 service list for Docket 26-05007 names 84 recipients. Vantage is not one of them — although the phase of that case now under way is the large-load electric service agreement for Vantage NV11.
The two dockets share no case number, no parcel and no applicant name. The link is stated in the project's own filings — “…pending in Docket No. 26-05007” — at the locators listed further down this page.
A later order cancelled the 22 September 2026 hearing and set the next one for 26 October 2026 at 10:00 a.m. in Carson City.
The dependency is stated in Docket 26-05028. What is not in Docket 26-05028 is anything that has happened since. Every dated step above was issued in the other docket, after this one went quiet. Each figure comes from a Commission record named further down this page.
This is one project, kept current from published records. Ask us to do this for a project of yours · see the live view.
Not being on a mailing list is not evidence that anyone is unaware of a case. A company may follow a proceeding it is not formally served in. What these records establish is where the dependency is stated, and what the other docket has done since — nothing about who knows what.
Public-record demonstration. 3 projects, shown using publicly available records. This is not an index of Nevada — it is every project maintained in this demonstration. Their inclusion does not indicate a relationship with Krowd Guide.
Krowd Guide records a dependency only where a record states one. Location gives context; it does not establish a relationship.
What is checked, and what is not
6 identified records are checked daily. 2 required records have no public identifier in the sources checked. Krowd Guide states those gaps rather than treating them as clear.
Not identified
- Nevada Construction Stormwater Permit
- Storey County Building Permit
This does not establish: That the checked records are correct — only that they were read and that each publisher returned the record requested · That no identifier exists for the records listed as not identified. None was found in the sources checked on the dates stated, which is a different fact · That the daily check runs unattended, unless the sentence above says it does. A scheduled job that has never fired is configured behaviour, not observed behaviour
8 distinct records underpin these states. One of them is counted once here and appears twice in the records below, because it plays two roles: it is a project's own observed state and it is also a permit another project's order depends on.
All projects — records, dates and what each does not establish
South Valley
Storey County, Nevada
- Applicant · SV RNO Property Owner 1 LLC (Docket 26-04026)
Temporary Power — The Commission has granted the application. The permit to construct issues only after four named permits are filed and Staff verify them.
Public Utilities Commission of Nevada · Docket 26-04026
Docket 26-04026: 81 filings are on record. 26 have been read in full, 2 partly, 53 not yet opened. 69 pages remain unread. The state below rests on what has been read, not on the whole docket.
Application granted, subject to compliance filings PERMIT NOT YET ISSUED
The Commission granted the application on 17 September 2026. Construction may not commence until a permit to construct issues, and that permit issues only after Commission Staff verify the compliance items the order lists.
Granted is not permit issued. No construction may commence until the permit issues.
The application, its filing date, the applicant, the facility, its capacity and its location.
This does not establish
- Approval, denial or permit issuance
- That construction may begin
From these records
- Docket 26-04026 · 20 April 2026
Application of SV RNO Property Owner 1 LLC, under the provisions of the Utility Environmental Protection Act, for a permit to construct the South Valley Temporary Power Generation Facility consisting of a temporary 144 MW natural gas-fueled electric generating facility and associated facilities to be located on private land in Storey County, Nevada.
On 17 September 2026 the Commission granted the application in Docket 26-04026 “as provided by and consistent with” that order.
This does not establish
- That a permit to construct has issued — the order states construction may not commence until it does
- That the compliance items have been filed, or verified by Commission Staff
- Any decision by the Nevada Division of Environmental Protection or Storey County on the permits the order requires
From these records
- Docket Nos. 26-04026 & 26-04027 · 17 September 2026This order decides a consolidated proceeding. Its second application, Docket 26-04027, is the Peru Ridge Self-Generation Project of PR RNO Property Owner 1, LLC — a different project, not this one.
The Application of SV RNO Property Owner 1 LLC, designated as Docket No. 26-04026, is granted as provided by and consistent with this order.
On 18 September 2026 the Bureau of Consumer Protection — the Nevada Attorney General's Consumer Advocate — filed a Notice of Intervention in Docket 26-04026, entering the proceeding as a party the day after the order granting the application. It states it intervenes under NRS 228.360 “with the intent of representing the public interest”.
This does not establish
- Any challenge to the order — the notice requests nothing of it, takes no exception to it, and seeks neither a stay nor reconsideration
- That the grant is in doubt, delayed, or under review
- A position by the Bureau on this project — the notice states no view on its merits
- That intervention was required here: the proceedings NRS 228.360(1)(a) obliges the Consumer Advocate to enter are those under NRS 704.7561 to 704.7595 and the general rate and deferred energy applications under NRS 704.061 to 704.110, and this application was filed under the Utility Environmental Protection Act at NRS 704.820 to 704.900. Whether that makes this entry discretionary is a reading for the Commission, not for Krowd Guide
From these records
- Docket 26-04026 · 18 September 2026The notice is filed in two dockets at once. Its second, Docket 26-04027, is the Peru Ridge Self-Generation Project of PR RNO Property Owner 1, LLC — a different project, not this one.
the BCP is a real party in interest and intervenes with the intent of representing the public interest regarding matters which will be presented in the foregoing proceeding
An exceptions deadline of 10 September 2026 at 12:00 p.m., stated identically by two Commission representations.
This does not establish
- That the date will hold — the Commission states events may be continued, rescheduled or cancelled
From these records
- Docket Nos. 26-04026 & 26-04027 · 3 September 2026This source covers a consolidated proceeding. Project State is showing only the South Valley-related evidence relevant to this portfolio view.
THIS ORDER IS NOT A FINAL ORDER AND MAY BE SUBSTANTIALLY REVISED PRIOR TO ENTRY OF A FINAL ORDER BY THE PUBLIC UTILITIES COMMISSION OF NEVADA
- September 2026 Commission Calendar · September 2026
All events may be continued, rescheduled, or cancelled at the discretion of the Presiding Officer.
The external approvals one authority identifies as still outstanding for this project, including the NDEP Class 1 OPTC air permit.
This does not establish
- The current state of those approvals
- Any binding requirement — this text sits inside a draft
From these records
- Docket Nos. 26-04026 & 26-04027 · 3 September 2026This source covers a consolidated proceeding. Project State is showing only the South Valley-related evidence relevant to this portfolio view.
THIS ORDER IS NOT A FINAL ORDER AND MAY BE SUBSTANTIALLY REVISED PRIOR TO ENTRY OF A FINAL ORDER BY THE PUBLIC UTILITIES COMMISSION OF NEVADA
Where the records disagree
Two official representations give different years for the same scheduled event.
This concerns the record, not the project's status.
- Public Utilities Commission of Nevada, Procedural Order No. 4: WEDNESDAY, SEPTEMBER 16, 2025, at 12:00 P.M.
- Public Utilities Commission of Nevada, September 2026 Commission Calendar: Sep 16 · 12:00PM · Answers to Exceptions · 26-04026
Krowd Guide has not resolved which controls. Both are shown as published.
Observed 21 September 2026
Nevada Division of Environmental Protection · AP7374-5094
Pending AQOP application
Determined administratively complete on 20 April 2026 — completeness is not approval.
Does not establish permit issuance.
The Division represents this application as pending on a register it refreshes monthly.
This does not establish
- Any conclusion beyond that representation
- The state as of today — the register refreshes monthly
From these records
- AP7374-5094 · Air Case 12882 · FIN A2745
Updated during the first week of each month
On the Division’s own pending register this application is marked as one where a 30-day public notice period IS planned prior to issuance. If that holds, a comment window opens before the air permit issues.
This does not establish
- When that notice period would start — the register names no date, and Krowd Guide has not been told one
- That the notice will occur: the register records what is planned, and a plan is not a commitment
- That the permit will issue, or that the application will be approved
- That the register is current today. It carries no timestamp of any kind — no last-updated stamp, no as-of line, no per-row date — only a stated cadence of “Updated during the first week of each month”. A stated cadence is not an observation, and the date shown beside this record is when Krowd Guide read the page
From these records
- AP7374-5094 · Air Case 12882 · FIN A2745
Updated during the first week of each month
The application was submitted on 5 March 2026 and determined administratively complete on 20 April 2026.
This does not establish
- Approval — the Division states completeness implies no agreement or endorsement
- Issuance, denial, public notice or technical review
From these records
- AP7374-5094 · FIN A2745 · Air Case 12882 · 20 April 2026
a Notification of Initial Completeness does not imply any agreement or endorsement by the BAPC regarding analysis, information, positions, or conclusions presented in the application.
Where the records disagree
The published date of submittal and the completeness letter give different dates.
This concerns the record, not the project's status.
- Nevada Division of Environmental Protection, Pending applications register: Official Date of Submittal (ODS) — 04/19/2026
- Nevada Division of Environmental Protection, Notification of Initial Completeness: administratively complete as of April 20, 2026
Krowd Guide has not resolved which controls. Both are shown as published.
Observed 22 September 2026
What it is waiting on
Nevada Division of Environmental Protection
AP7374-5094
the Class 1 OPTC air permit the Commission's order requires before the permit to construct issues
Observed as a pending application, determined administratively complete on 20 April 2026. Completeness is not approval.
The Commission's permit to construct cannot issue until this permit is filed with it and Staff verify it.
Established by
- Docket Nos. 26-04026 & 26-04027 — ordering paragraph 4(c) · 17 September 2026This order decides a consolidated proceeding. Its second application, Docket 26-04027, is the Peru Ridge Self-Generation Project of PR RNO Property Owner 1, LLC — a different project, not this one.
The Application of SV RNO Property Owner 1 LLC, designated as Docket No. 26-04026, is granted as provided by and consistent with this order.
Nevada Division of Environmental Protection, Bureau of Air Pollution Control
NDEP AP16295090 · Surface Area Disturbance
this permit, which the Commission's order requires before the permit to construct issues
The Commission's order named this permit without a number. NDEP's own air-permit collection carries it under facility A2745 as permit AP16295090, with the bureau's own permit class recorded as “SAD”. Three documents are on file: two typed “permit application and correspondence” and one typed “permit”. The permit is also NOT on the bureau's pending register, read the same day across 190 rows. Those two facts point the same way and do not settle it: a document typed “permit” being on file is not a statement that a permit issued, is effective, or is current, and the bureau's type vocabulary is coarse. Krowd Guide reports both and determines neither.
The order establishes that this permit is required. It does not establish whether one has been applied for, issued or refused.
Established by
- Docket Nos. 26-04026 & 26-04027 — ordering paragraph 4(a) · 17 September 2026This order decides a consolidated proceeding. Its second application, Docket 26-04027, is the Peru Ridge Self-Generation Project of PR RNO Property Owner 1, LLC — a different project, not this one.
The Application of SV RNO Property Owner 1 LLC, designated as Docket No. 26-04026, is granted as provided by and consistent with this order.
- AP16295090 — permit AP16295090, facility A2745
SAD
Nevada Division of Environmental Protection
Nevada Construction Stormwater Permit
this permit, which the Commission's order requires before the permit to construct issues
No public identifier was found in the sources checked as of 22 September 2026. EPA's facility registry was queried for this location and returned no registered facility within 5 km — the query succeeded and the answer was empty. NDEP's public document collections cover mining and air, not water-pollution construction permits. This states what was checked and what those checks returned. It does not establish that no identifier exists, only that none was found in these sources on this date.
The Commission's order requires this permit before a permit to construct can issue. Krowd Guide has no state for it — see the record note above for what was checked.
Established by
- Docket Nos. 26-04026 & 26-04027 — ordering paragraph 4(b) · 17 September 2026This order decides a consolidated proceeding. Its second application, Docket 26-04027, is the Peru Ridge Self-Generation Project of PR RNO Property Owner 1, LLC — a different project, not this one.
The Application of SV RNO Property Owner 1 LLC, designated as Docket No. 26-04026, is granted as provided by and consistent with this order.
Storey County
Storey County Building Permit
this permit, which the Commission's order requires before the permit to construct issues
No public identifier was found in the sources checked as of 22 September 2026. Storey County publishes permit APPLICATION FORMS and a fee-payment page; its searchable registers are the Recorder's records, property taxes, the assessment roll and historic records — read across 3,000 archived page captures, with no permit search among them. The county website was unreachable on 22 September 2026, having been archived as reachable on 24 August, so this was read from the archive rather than assumed. This states what was checked and what those checks returned. It does not establish that no identifier exists, only that none was found in these sources on this date.
The Commission's order requires this permit before a permit to construct can issue. Krowd Guide has no state for it — see the record note above for what was checked.
Established by
- Docket Nos. 26-04026 & 26-04027 — ordering paragraph 4(d) · 17 September 2026This order decides a consolidated proceeding. Its second application, Docket 26-04027, is the Peru Ridge Self-Generation Project of PR RNO Property Owner 1, LLC — a different project, not this one.
The Application of SV RNO Property Owner 1 LLC, designated as Docket No. 26-04026, is granted as provided by and consistent with this order.
Big Ledge Discharge Closure Project
Elko County, Nevada
- Applicant · National Oilwell Varco, L.P. (Water Pollution Control Permit NEV2026122)
Water Pollution Control Permit — One authority holds the decision this dependency is waiting on.
Nevada Division of Environmental Protection, Bureau of Mining Regulation and Reclamation · NEV2026122
Decision to issue SUBJECT TO APPEAL
NDEP’s Administrator decided on 13 October 2026 to issue new Water Pollution Control Permit NEV2026122 to National Oilwell Varco, L.P. NDEP states the permit becomes effective on 28 October 2026.
A decision to issue is not an effective permit. NDEP states the permit becomes effective on 28 October 2026, and that the decision may be appealed to the State Environmental Commission until 5:00 p.m. on 23 October 2026.
The bureau’s public notice page states that an application for a new Water Pollution Control Permit has been filed, and names the applicant, the facility, its purpose and its location.
This does not establish
- Approval, denial or permit issuance
- That any discharge has occurred or may begin
- That the permit is new. This is the NOTICE PAGE’s characterisation, quoted verbatim. The same bureau’s document collection types the filing “PERMIT APPLICATION / RENEWAL”, which does not distinguish the two — see the record conflict shown with this state
From these records
- Water Pollution Control Permit NEV2026122 · 3 September 2026
Date of Web Posting: 09/03/2026 · Deadline for Comments: 10/03/2026
- NEV2026122 · 3 September 2026
an application for a new Water Pollution Control Permit for the Big Ledge Discharge Closure Project, a dewatering management facility, has been properly filed with the NDEP in Carson City
NDEP lists this as a 5-Year Discharge Permit Application / Renewal, dated 16 April 2026, in the bureau’s own document collection.
This does not establish
- Whether this is a new permit or a renewal. The bureau’s type token is “PERMIT APPLICATION / RENEWAL”, which covers both, and Krowd Guide does not choose between them. The bureau’s public notice page separately calls it an application for a NEW permit; both are shown as published and neither is resolved
- Approval, denial or permit issuance
- That the collection is complete. It was read for 2026 only — 675 rows — so a document filed under this permit in another year was not looked for
From these records
- NEV2026122 · 16 April 2026
PERMIT APPLICATION / RENEWAL
The bureau published the notice on 3 September 2026 and states a comment deadline of 3 October 2026.
This does not establish
- That any comment has been filed
- What the bureau will decide, or when
From these records
- Water Pollution Control Permit NEV2026122 · 3 September 2026
Date of Web Posting: 09/03/2026 · Deadline for Comments: 10/03/2026
- Public notices index · 3 September 2026
Issue new Water Pollution Control Permit NEV2026112 to National Oilwell Varco, L.P. Public comment period is from September 3, 2026 to October 3, 2026
On 13 October 2026 NDEP’s Administrator decided to issue new Water Pollution Control Permit NEV2026122 to National Oilwell Varco, L.P. NDEP states that the permit becomes effective on 28 October 2026, that the decision may be appealed to the State Environmental Commission until 5:00 p.m. on 23 October 2026, and that no comments were received during the public comment period.
This does not establish
- That the permit is in effect today. NDEP states it becomes effective on 28 October 2026
- Whether an appeal has been or will be filed
- That any discharge has occurred or may begin
- What the permit’s conditions require. The permit document is the record
From these records
- WPCP NEV 2026122 · 13 October 2026
The Administrator of the Nevada Division of Environmental Protection (NDEP) has decided to issue new Water Pollution Control Permit NEV2026122 to National Oilwell Varco, L.P.
- NEV2026122 · 12 October 2026
Revision 00: Permit effective 28 October 2026
Where the records disagree
Two official records of the same bureau describe this permit differently: one calls it an application for a NEW permit, the other types it as an application OR renewal without distinguishing.
This concerns the record, not the project’s status.
- Nevada Division of Environmental Protection, Public notice page for the proposed action: an application for a new Water Pollution Control Permit
- Nevada Division of Environmental Protection, Bureau document collection, document dated 16 April 2026: 5-Year Discharge Permit Application, typed “PERMIT APPLICATION / RENEWAL”
Krowd Guide has not resolved which controls. Both are shown as published. The bureau’s type token covers application and renewal alike and so does not distinguish them, and Krowd Guide does not infer one from the other.
Where the records disagree
NDEP’s September records also carry a second permit number for this permit. Its October decision documents use NEV2026122 throughout.
This concerns the record, not the project's status.
- Nevada Division of Environmental Protection, Public notices listing, 3 September summary: NEV2026112
- Nevada Division of Environmental Protection, Draft permit, 3 September: page headers, pages 2–15: NEV2026112
- Nevada Division of Environmental Protection, Draft fact sheet, 3 September: page 6: NEV2026112
- Nevada Division of Environmental Protection, Notice of Proposed Action, its page, the draft permit’s cover and the draft fact sheet, 3 September: NEV2026122
- Nevada Division of Environmental Protection, Notice of Decision, final permit and final fact sheet, 12–13 October: NEV2026122
- Nevada Division of Environmental Protection, Bureau document collection, 2025–2027: NEV2026122 (no record under NEV2026112)
NDEP’s 13 October decision, final permit and final fact sheet use NEV2026122 consistently. Why the September records also carry NEV2026112, and whether NDEP has formally clarified it, is not established. Krowd Guide has found no such clarification and shows both as published.
Observed 14 October 2026
Vantage NV11
Storey County, Nevada
- Applicant · Sierra Pacific Power Company d/b/a NV Energy (Docket 26-05028)
- Customer under the agreement · Vantage Data Centers NV11, LLC (Docket 26-05028)
- Owner of record of the parcel · Vantage Data Centers NV11, LLC (Parcel 005-041-95)
- Applicant for state tax incentives · Vantage Data Centers NV11, LLC (Board packet, agenda item 8-B (March 2024))
Large Load Electric Service — This project's own proceeding is waiting on a separate proceeding.
Public Utilities Commission of Nevada · Docket 26-05028
Set out, awaiting a separate proceeding NOT A DECISION
This project’s own proceeding has been set out by the presiding officer until a separate proceeding reaches its final order.
Being set out establishes a schedule, not an outcome. Nothing here establishes that the agreement will be approved, or when.
The application was filed on 27 May 2026. On 3 June 2026 the applicant amended it so that the customer is named Vantage Data Centers NV11, LLC throughout, where the filing had named it Vantage Data Centers NV1, LLC in places. The presiding officer’s Procedural Order No. 1 records the filing date as 3 June 2026.
This does not establish
- Why the order records 3 June rather than 27 May — no record read states it.
- Anything about the agreement’s terms or whether it will be approved.
From these records
- Docket 26-05028 · 27 May 2026
The Company’s proposed supply side resources to serve Customer is presented to the Commission contemporaneous with this Application, in Docket No. 26-05007.
- Docket 26-05028 · 3 June 2026
On May 27, 2026, Sierra Pacific Power Company d/b/a NV Energy filed its Application for approval of a Large Load Electric Service Agreement (“LLESA”) with Vantage Data Centers NV11, LLC (“Vantage”) with the Public Utilities Commission of Nevada. After filing, it was discovered that Vantage Data Centers NV11, LLC is incorrectly referenced as Vantage Data Centers NV1, LLC in multiple instances within the filing. This letter serves to clarify that the filing should reference Vantage Data Centers NV11, LLC throughout the application and supporting materials.
- Docket 26-05028 · 22 July 2026
The parties ask that the matter be set out to allow for resolution of LLESA issues pending in Docket No. 26-05007 … the continued prehearing conference shall be set in January, after the issuance of the final order in Docket No. 26-05007.
The applicant states that the agreement “contains provisions designed to mitigate the risk associated with the customer’s large load request.” The agreement’s unredacted pages, testimony and certain workpapers were filed under seal, so those terms are not public in the filings reviewed.
This does not establish
- What the risk-mitigation provisions are, or how effective they are — the terms are under seal.
- That the Commission has found those provisions adequate — this is the applicant’s statement. No Commission finding on the adequacy of these provisions was identified in the records reviewed as of 9 October 2026.
- That the terms will stay unavailable — a later order, redacted filing or lawful disclosure could make some of them public; Krowd Guide keeps checking.
From these records
- Docket 26-05028 · 29 May 2026
Sierra Pacific Power Company is requesting the Public Utilities Commission of Nevada issue an Order approving a large load electric service agreement to provide electric service to serve Vantage Data Centers NV11, LLC’s facilities, located in McCarran, Nevada. The LLESA contains provisions designed to mitigate the risk associated with the customer’s large load request.
- Docket 26-05028 · 29 May 2026
Portions of the filing accompanying this transmittal letter are to be kept under seal pursuant to NAC § 703.527 et seq. … contains the unredacted pages from the LLESA and testimony of Janet Wells and Misha Pascal, and certain workpapers … The Company requests that this confidential information remain under seal for a period of at least five years following the expiration or earlier termination of the attached LLESA.
This project’s own proceeding is paused on the presiding officer’s schedule until a separate proceeding issues its final order.
This does not establish
- Set out is not denied, and not withdrawn.
- A schedule does not establish what the outcome will be.
- A continued conference date is not a decision date.
From these records
- Docket 26-05028 · 22 July 2026
The parties ask that the matter be set out to allow for resolution of LLESA issues pending in Docket No. 26-05007 … the continued prehearing conference shall be set in January, after the issuance of the final order in Docket No. 26-05007.
The order that set this matter out also scheduled what comes next: a CONTINUED PREHEARING CONFERENCE on Tuesday 26 January 2027 at 11:00 a.m. at the Commission’s offices in Carson City, with videoconference. The pause has a date attached to it in the record.
This does not establish
- That the conference will be held on that date — the Commission may continue, reschedule or cancel a scheduled event, and this one is expressly tied to the final order issuing in the separate proceeding first
- That a decision on the agreement comes at that conference — a prehearing conference sets a schedule, it does not decide the application
- Anything about the outcome of either proceeding
From these records
- Docket 26-05028 · 22 July 2026
The parties ask that the matter be set out to allow for resolution of LLESA issues pending in Docket No. 26-05007 … the continued prehearing conference shall be set in January, after the issuance of the final order in Docket No. 26-05007.
The separate proceeding this project waits on issued an order on 10 September 2026 that, by its own terms, settles one phase of that proceeding.
This does not establish
- An order in the separate proceeding is not an order in this one.
- Settling one phase does not establish that the phase covering this project’s agreement is settled.
- Nothing here establishes that the awaited final order has issued.
From these records
- Docket 26-05007 · 10 September 2026This record’s own caption names a proceeding wider than this project. It is shown as the source captions it.
The Commission accepts the stipulation, appended hereto as Attachment A, and grants the application as modified by the stipulation.
- Docket 26-05007 · 20 August 2026This record’s own caption names a proceeding wider than this project. It is shown as the source captions it.
The dated steps in the separate proceeding are set by its Procedural Order No. 6 of 6 October 2026, which revises the schedule first set on 20 August 2026 (as the order of 24 September 2026 also did) and keeps the 22 September 2026 Phase I hearing cancelled.
This does not establish
- A dated step is when the matter is next taken up. It does not establish what will be decided.
- Nothing here establishes that the agreement will be approved, in any form.
- A later order can replace this schedule as this one replaced the order before it.
- The 2 October filing is a deadline for prepared direct testimony by named participants. It is not a public comment deadline, and nothing here establishes one.
From these records
- Docket 26-05007 · 6 October 2026
The procedures and schedule adopted in Procedural Order No. 3 are revised as follows, with new language in bold italics … The September 22, 2026, Phase I ESP Hearing is cancelled. … c. Phase III — Supply Side, Load Forecast, etc. … The procedural schedule and discovery processes set forth in paragraphs 31-36 are adopted.
- Docket 26-05007 · 24 September 2026
b. Phase II — DSM, DRP, TEP, LLESA (Including LLESA, and any testimony regarding the Large Load Tariff and agreement proposals from Docket No. 20-08014) … The September 22, 2026, Phase I ESP Hearing is cancelled. … Staff shall, and BCP and Intervenors may, file … on or before FRIDAY, OCTOBER 2, 2026, by 12:00 p.m. supplemental PREPARED DIRECT TESTIMONY containing specific recommendations should the Commission wish to proceed with approval of some form of the LLESA. … The presiding officer will hold a HEARING starting on MONDAY, OCTOBER 26, 2026, at 10:00 a.m., at the Commission’s offices in Carson City, Nevada.
- Docket 26-05007 · 20 August 2026This record’s own caption names a proceeding wider than this project. It is shown as the source captions it.
Observed 15 September 2026
What it is waiting on
Public Utilities Commission of Nevada
Docket 26-05007
Docket 26-05007: 400 filings are on record. 28 have been read in full, 6 partly, 359 not yet opened, 7 could not be read. 201 pages remain unread. The state below rests on what has been read, not on the whole docket.
the final order in the separate proceeding this project's own docket was set out to await
On 10 September, an order settled Phase I of the outside matter.
Phase II, which includes the form Large Load Electric Service Agreement that the Vantage NV11 agreement is based on, remains open.
Last dated step in that matter (passed)
2 October 2026 — supplemental prepared direct testimony on whether to proceed with approval of some form of the Large Load Electric Service Agreement, set by Procedural Order No. 4 of 24 September 2026 — which also set the Phase II hearing for 26 October 2026 at 10:00 a.m. in Carson City
A dated step is when the matter is next taken up. It does not establish what will be decided.
Established by
- Docket 26-05028 — footnote 2 · 27 May 2026
The Company’s proposed supply side resources to serve Customer is presented to the Commission contemporaneous with this Application, in Docket No. 26-05007.
- Docket 26-05028 — paragraph 6 · 22 July 2026
The parties ask that the matter be set out to allow for resolution of LLESA issues pending in Docket No. 26-05007 … the continued prehearing conference shall be set in January, after the issuance of the final order in Docket No. 26-05007.
Verifying any of this
Every docket number above can be searched at the Public Utilities Commission of Nevada's own document search. Krowd Guide names the docket, the document type and the date rather than linking a document, because the Commission's service does not issue durable links — a link published here would break for whoever read it next.
Named in these records but carrying no state here, and therefore not checked: 26-04027.