Nevada Project State — 3 public-record projects

3 Nevada projects shown from published public records: what each one is waiting on, what the records establish, and what they do not. Every state carries its own observation date; the oldest is 13 September 2026.

Public-record demonstration. 3 projects, shown using publicly available records. This is not an index of Nevada — it is every project maintained in this demonstration. Their inclusion does not indicate a relationship with Krowd Guide.

Krowd Guide records a dependency only where a record states one. Location gives context; it does not establish a relationship.

South Valley

Storey County, Nevada · applicant of record SV RNO Property Owner 1 LLC

Temporary Power — The Commission has granted the application. The permit to construct issues only after four named permits are filed and Staff verify them.

Public Utilities Commission of Nevada · Docket 26-04026

Application granted, subject to compliance filings PERMIT NOT YET ISSUED

The Commission granted the application on 17 September 2026. Construction may not commence until a permit to construct issues, and that permit issues only after Commission Staff verify the compliance items the order lists.

Granted is not permit issued. No construction may commence until the permit issues.

Observed 21 September 2026

Nevada Division of Environmental Protection · AP7374-5094

Pending AQOP application

Determined administratively complete on 20 April 2026 — completeness is not approval.

Does not establish permit issuance.

Observed 13 September 2026

What it is waiting on

Nevada Division of Environmental Protection

AP7374-5094

the Class 1 OPTC air permit the Commission's order requires before the permit to construct issues

Observed as a pending application, determined administratively complete on 20 April 2026. Completeness is not approval.

The Commission's permit to construct cannot issue until this permit is filed with it and Staff verify it.

Established by

  • Docket Nos. 26-04026 & 26-04027 — ordering paragraph 4(c)

Nevada Division of Environmental Protection, Bureau of Air Pollution Control

Surface Area Disturbance Permit

this permit, which the Commission's order requires before the permit to construct issues

Krowd Guide has not yet looked at this authority's record for this permit.

The order establishes that this permit is required. It does not establish whether one has been applied for, issued or refused.

Established by

  • Docket Nos. 26-04026 & 26-04027 — ordering paragraph 4(a)

Nevada Division of Environmental Protection

Nevada Construction Stormwater Permit

this permit, which the Commission's order requires before the permit to construct issues

Krowd Guide has not yet looked at this authority's record for this permit.

The order establishes that this permit is required. It does not establish whether one has been applied for, issued or refused.

Established by

  • Docket Nos. 26-04026 & 26-04027 — ordering paragraph 4(b)

Storey County

Storey County Building Permit

this permit, which the Commission's order requires before the permit to construct issues

Krowd Guide has not yet looked at this authority's record for this permit.

The order establishes that this permit is required. It does not establish whether one has been applied for, issued or refused.

Established by

  • Docket Nos. 26-04026 & 26-04027 — ordering paragraph 4(d)

Big Ledge Discharge Closure Project

Elko County, Nevada · applicant of record National Oilwell Varco, L.P.

Water Pollution Control Permit — One authority holds the decision this dependency is waiting on.

Nevada Division of Environmental Protection, Bureau of Mining Regulation and Reclamation · NEV2026122

Application filed, comment period open NOT A DECISION

A new Water Pollution Control Permit has been applied for and the bureau has opened public comment.

Observed 13 September 2026

Vantage NV11

Storey County, Nevada · applicant of record Vantage Data Centers NV11, LLC

Large Load Electric Service — This project's own proceeding is waiting on a separate proceeding.

Public Utilities Commission of Nevada · Docket 26-05028

Set out, awaiting a separate proceeding NOT A DECISION

This project’s own proceeding has been set out by the presiding officer until a separate proceeding reaches its final order.

Being set out establishes a schedule, not an outcome. Nothing here establishes that the agreement will be approved, or when.

Observed 15 September 2026

What it is waiting on

Public Utilities Commission of Nevada

Docket 26-05007

the final order in the separate proceeding this project's own docket was set out to await

An order issued on 10 September 2026 accepting a stipulation and granting the application as modified. By its own terms it settles one phase of that proceeding.

The phase covering this project's own service agreement remains open, and the final order this docket was set out to await has not issued.

Established by

  • Docket 26-05028 — footnote 2
  • Docket 26-05028 — paragraph 6

Verifying any of this

Every docket number above can be searched at the Public Utilities Commission of Nevada's own document search. Krowd Guide names the docket, the document type and the date rather than linking a document, because the Commission's service issues a short-lived handle — one captured and re-requested about twenty minutes later returned HTTP 404 while a freshly issued one returned the same document. A link published here would break for whoever read it next.

Named in these records but carrying no state here, and therefore not checked: 26-04027.